Terminal evaluation of Rural energy technology promotion project

Report Cover Image
Evaluation Plan:
2021-2025, Ethiopia
Evaluation Type:
Final Project
Planned End Date:
10/2021
Completion Date:
11/2021
Status:
Completed
Management Response:
Yes
Evaluation Budget(US $):
45,000

Share

Document Type Language Size Status Downloads
Download document UNDP-GEF-TE-TOR-RET_Project_TE_May_07_2021_ENGLISH_Final_Clean version.doc tor English 511.50 KB Posted 228
Download document Final TE Report of RET Project-Ethiopia-10.11.2021.pdf report English 1953.48 KB Posted 216
Title Terminal evaluation of Rural energy technology promotion project
Atlas Project Number: 00086749
Evaluation Plan: 2021-2025, Ethiopia
Evaluation Type: Final Project
Status: Completed
Completion Date: 11/2021
Planned End Date: 10/2021
Management Response: Yes
UNDP Signature Solution:
  • 1. Poverty
Corporate Outcome and Output (UNDP Strategic Plan 2018-2021)
  • 1. Output 2.1.1 Low emission and climate resilient objectives addressed in national, sub-national and sectoral development plans and policies to promote economic diversification and green growth
SDG Goal
  • Goal 13. Take urgent action to combat climate change and its impacts
  • Goal 7. Ensure access to affordable, reliable, sustainable and modern energy for all
  • Goal 9. Build resilient infrastructure, promote inclusive and sustainable industrialization and foster innovation
SDG Target
  • 13.2 Integrate climate change measures into national policies, strategies and planning
  • 7.1 By 2030, ensure universal access to affordable, reliable and modern energy services
  • 9.4 By 2030, upgrade infrastructure and retrofit industries to make them sustainable, with increased resource-use efficiency and greater adoption of clean and environmentally sound technologies and industrial processes, with all countries taking action in accordance with their respective capabilities
Evaluation Budget(US $): 45,000
Source of Funding: gef
Evaluation Expenditure(US $): 30,000
Joint Programme: No
Joint Evaluation: No
Evaluation Team members:
Name Title Email Nationality
Mr. Vinod Kumar Jain International Consultant vkmnre@gmail.com INDIA
Mr. Abera Gayesa Tirfi Local Consultant abera.gayesa@gmail.com ETHIOPIA
GEF Evaluation: Yes
GEF Project Title: Terminal evaluation of Rural energy technology promotion project
Evaluation Type: Terminal Evaluation
Focal Area: Climate Change
Project Type: FSP
GEF Phase: GEF-5
GEF Project ID: 5501
PIMS Number: 5200
Key Stakeholders: Ministry of Water, Irrigation and Energy, UNCDF, Development Bank of Ethiopia, GEF
Countries: ETHIOPIA
Lessons
Findings
Recommendations
1

Evaluation recommendation 1. All Technical Reports, Knowledge Products, and other relevant information/data produced under the project be made available to the public on the closure of the project

2

Evaluation recommendation 2. Establishment of Region-wise Testing and Certification Facilities for Cookstoves

3

Evaluation recommendation 3.   Enable Credit Risk-Guarantee Facility and Other RET Products to Continue

4

Evaluation recommendation 4.    Tracking of Socio-economic and other Developmental Benefits such as Health and Reduction in GHG Emissions

5

Evaluation recommendation 5.    Design and Implement Sustainability Build-up and Exit Strategy

1. Recommendation:

Evaluation recommendation 1. All Technical Reports, Knowledge Products, and other relevant information/data produced under the project be made available to the public on the closure of the project

Management Response: [Added: 2021/11/17]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
1.1 Organize and prepare necessary documents.
[Added: 2021/11/17] [Last Updated: 2021/12/14]
PMU, UNDP 2021/12 Completed Action completed History
1.2 Delivery of the documents to MoWE Energy sector.
[Added: 2021/11/17] [Last Updated: 2021/12/14]
PMU 2021/12 Completed Action completed History
2. Recommendation:

Evaluation recommendation 2. Establishment of Region-wise Testing and Certification Facilities for Cookstoves

Management Response: [Added: 2021/11/17]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
2.1 Organize a discussion forum with MoWE and regional energy bureaus
[Added: 2021/11/17] [Last Updated: 2021/12/14]
PMU, UNDP 2021/12 Completed Action completed History
2.2 Provide Technical Support to MoWE on purchasing of equipments.
[Added: 2021/11/17] [Last Updated: 2021/12/14]
PMU, UNDP 2021/12 Completed Action completed History
2.3 Advise Regions to deploy experts to the incubation canter
[Added: 2021/11/17] [Last Updated: 2021/12/14]
PMU 2021/12 Completed Action completed History
3. Recommendation:

Evaluation recommendation 3.   Enable Credit Risk-Guarantee Facility and Other RET Products to Continue

Management Response: [Added: 2021/11/17]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
3.1 Organize a meeting with the SC and present the importance of the recommendation
[Added: 2021/11/17] [Last Updated: 2021/12/14]
PMU, UNDP 2022/03 Initiated History
3.2 Document discussion minutes and directions
[Added: 2021/11/17] [Last Updated: 2021/12/14]
PMU 2022/03 Initiated History
3.3 Implement the decision of SC recommendation
[Added: 2021/11/17] [Last Updated: 2021/12/14]
PMU 2022/03 Initiated History
4. Recommendation:

Evaluation recommendation 4.    Tracking of Socio-economic and other Developmental Benefits such as Health and Reduction in GHG Emissions

Management Response: [Added: 2021/11/17]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
4.1 Organize a discussion with regional energy bureaus about socio-economic benefits
[Added: 2021/11/17] [Last Updated: 2021/12/14]
PMU 2021/12 Completed Action completed History
4.2 Promote socio-economic benefits in RET dissemination
[Added: 2021/11/17] [Last Updated: 2021/12/14]
Regional Energy Unit 2022/02 Completed Action completed History
5. Recommendation:

Evaluation recommendation 5.    Design and Implement Sustainability Build-up and Exit Strategy

Management Response: [Added: 2021/11/17] [Last Updated: 2021/11/18]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
5.1.Prepare Exist strategy
[Added: 2021/11/17] [Last Updated: 2021/12/14]
PMU 2022/03 Initiated History
5.2 Organize a meeting with concerned stakeholders on the exit strategy
[Added: 2021/11/17] [Last Updated: 2021/12/14]
PMU , UNDP 2022/03 Initiated History
5.3 Implement Exit strategy
[Added: 2021/11/17] [Last Updated: 2021/12/14]
MoWE and Regional Energy Bureau 2022/03 Initiated History

Latest Evaluations

Contact us

1 UN Plaza
DC1-20th Floor
New York, NY 10017
Tel. +1 646 781 4200
Fax. +1 646 781 4213
erc.support@undp.org