State bodies instituional capacities strengthened at national and local level for efficient, accountable and inclusive governance and effective service delivery

Report Cover Image
Evaluation Plan:
2009-2013, Angola
Evaluation Type:
Outcome
Planned End Date:
12/2009
Completion Date:
09/2009
Status:
Completed
Management Response:
Yes
Evaluation Budget(US $):
24,200

Share

Document Type Language Size Status Downloads
Download document report English Posted 641
Download document Angola Governance Outcome Evaluation Report Final.doc report English 177.50 KB Posted 2671
Title State bodies instituional capacities strengthened at national and local level for efficient, accountable and inclusive governance and effective service delivery
Atlas Project Number:
Evaluation Plan: 2009-2013, Angola
Evaluation Type: Outcome
Status: Completed
Completion Date: 09/2009
Planned End Date: 12/2009
Management Response: Yes
Focus Area:
  • 1. Democratic Governance
Corporate Outcome and Output (UNDP Strategic Plan 2014-2017)
  • 1. National, regional and local levels of governance expand their capacities to reduce conflict and manage the equitable delivery of public services
  • 2. Effective, responsive, accessible and fair justice systems promote the rule of law, including both formal and informal processes, with due consideration on the rights of the poor, women and vulnerable groups
  • 3. Strengthened national, regional and local level capacity to mainstream gender equality and women's empowerment in government policies and institutions
  • 4. State bodies institutional capacity strengthened at national and local level for efficient, accountable and inclusive governance and effective service delivery
Evaluation Budget(US $): 24,200
Source of Funding:
Joint Programme: No
Joint Evaluation: No
Evaluation Team members:
Name Title Email Nationality
Team Leader
Team Leader
GEF Evaluation: No
Key Stakeholders:
Countries: ANGOLA
Comments: In 2009, we the CO will evaluate the contribution to the decentralization process in Angola.
Lessons
Findings
Recommendations
1 UNDP should design a clear strategy for ensuring that partners and donors are given visibility in project implementation. This should include measures to ensure that other UN agencies and CSOs are actively involved in the two projects and the implementation of CPAP as a whole.
2 There is need for UNDP to develop and adopt a body of indicators for assessing the impact of all its activities. Emphasis should be placed on whether skills are created, enhanced, mobilized and utilized post training.
3 UNDP should allow the Justice Reform & Modernization project to expire as it does not support the cadre of stakeholders and duty bearers in the justice sector.
4 UNDP should conduct an needs assessment of the entire justice system including government institutions, traditional authorities, Assembly, CSO?s, (I)NGOs and other relevant stakeholders and duty bearers.
5 UNDP Angola, pursuant to UNDP corporate principals and findings from justice sector and assembly needs assessments should combine the new justice support activities and the support to the Assembly activities under a new project ?Access to Justice?.
6 UNDP should appoint an interim Head of Democratic Governance, while recruiting a ?permanent? staff to oversee, coordinate and manage assessments and project amendments or development.
7 UNDP should continue to utilize the Provincial Programme Coordinators to implement the new Democratic Governance projects portfolios, to ensure that there is continuous communication and sharing of information.
8 To ensure that donors and partners are adequately informed of progress in project implementation, UNDP should frequently (if possible on monthly basis) prepare progress reports and hold frequent briefing meetings with donors and partners.
1. Recommendation: UNDP should design a clear strategy for ensuring that partners and donors are given visibility in project implementation. This should include measures to ensure that other UN agencies and CSOs are actively involved in the two projects and the implementation of CPAP as a whole.
Management Response: [Added: 2010/01/28]

UN has decided and instructed all projects to, as of 2010 AWPs, allocate a budget of at least 1% of its budget for advocacy and communication activities

Key Actions:

2. Recommendation: There is need for UNDP to develop and adopt a body of indicators for assessing the impact of all its activities. Emphasis should be placed on whether skills are created, enhanced, mobilized and utilized post training.
Management Response: [Added: 2010/01/28]

Through the DLG project, UNDP is developing a set of governance indicators to assess the impact of the support provided to local administrations.

Key Actions:

3. Recommendation: UNDP should allow the Justice Reform & Modernization project to expire as it does not support the cadre of stakeholders and duty bearers in the justice sector.
Management Response: [Added: 2010/01/28]

Recommendation fully implemented. The project has been closed in December 2009 as planned.

Key Actions:

4. Recommendation: UNDP should conduct an needs assessment of the entire justice system including government institutions, traditional authorities, Assembly, CSO?s, (I)NGOs and other relevant stakeholders and duty bearers.
Management Response: [Added: 2010/01/28]

UNDP will develop a access to justice project, which will take this recommendation into account.

Key Actions:

5. Recommendation: UNDP Angola, pursuant to UNDP corporate principals and findings from justice sector and assembly needs assessments should combine the new justice support activities and the support to the Assembly activities under a new project ?Access to Justice?.
Management Response: [Added: 2010/01/28]

In the designing of the new project Access to Justice, UNDP will explore the best way of combining justice and assembly activities.

Key Actions:

6. Recommendation: UNDP should appoint an interim Head of Democratic Governance, while recruiting a ?permanent? staff to oversee, coordinate and manage assessments and project amendments or development.
Management Response: [Added: 2010/01/28]

The recommendation has already been implemented. A new interim Head of Democratic Governance has been nominated.

Key Actions:

7. Recommendation: UNDP should continue to utilize the Provincial Programme Coordinators to implement the new Democratic Governance projects portfolios, to ensure that there is continuous communication and sharing of information.
Management Response: [Added: 2010/01/28]

UNDP is taking full advantage of provincial project coordinators and technical teams to implement activities of both Decentralization and Local Governance Projects. The same approach will be applied with new governance projects.

Key Actions:

8. Recommendation: To ensure that donors and partners are adequately informed of progress in project implementation, UNDP should frequently (if possible on monthly basis) prepare progress reports and hold frequent briefing meetings with donors and partners.
Management Response: [Added: 2010/01/28]

The CO has decided to be more systematic with projects quarterly reports and dissemination to donors and partners. Periodic meetings with partners are held, such as project boards, thematic meetings with donors and partners.

Key Actions: