Evaluation of UNDP Romania Country Programme 2010-2012

Report Cover Image
Evaluation Plan:
2010-2015, Romania
Evaluation Type:
Others
Planned End Date:
06/2012
Completion Date:
07/2012
Status:
Completed
Management Response:
Yes
Evaluation Budget(US $):
25,000

Share

Document Type Language Size Status Downloads
Download document UNDP CO evaluation2012.pdf report English 1410.64 KB Posted 1180
Title Evaluation of UNDP Romania Country Programme 2010-2012
Atlas Project Number:
Evaluation Plan: 2010-2015, Romania
Evaluation Type: Others
Status: Completed
Completion Date: 07/2012
Planned End Date: 06/2012
Management Response: Yes
Corporate Outcome and Output (UNDP Strategic Plan 2014-2017)
Evaluation Budget(US $): 25,000
Source of Funding:
Joint Programme: No
Joint Evaluation: Yes
  • Joint with Ministry of Foreign Affairs
Evaluation Team members:
Name Title Email Nationality
Jakob Simonsen Team Leader
Irina Pascu Team Leader
GEF Evaluation: No
Key Stakeholders: Ministry of Foreign Affairs
Countries: ROMANIA
Comments: Evaluation of the strategic CPD objective, that of advancing of Romania?s role in international development cooperation in accordance with Romania?s geopolitical and strategic position and profile as an active and responsible member of the European Union and the international community. At the end of the programming period, the Government of Romania will have at its disposal, a Romania-UN(DP) partnership model which will produce innovative and multi-actor knowledge and international networking base for Romania?s contribution to internationally agreed development goals.
Lessons
Findings
Recommendations
1 1.1 End representational presence of UNDP in Romania by end 2012.
2 1.2 Ensure minimal critical presence in CO Romania to ensure monitoring, trouble-shooting and direct line of communication to corporate UNDP (BERA, RBEC/BRC).
3 1.3 Increase visibility of CP in Romania by telling the success stories through beneficiaries to nurture national interest in and demand for international development cooperation as well as facilitate dialogue with the EU and traditional donors on possible ?new partnership models?.
4 1.4 Complete legal framework for completion of residual programme
5 1.5 Increase national ownership and coordination to ensure impact and sustainability of the CP. Ensure coordination with and among national implementing partners.
6 Issue 2: Successor arrangement 2.12.1 Ensure political will and ownership/capacity in the MFA to reach sustainability of a national ODA structure by 2015
7 2.2 Ensure a targeted and focused approach to Romanian development cooperation, going from simple to complex in consonance with the gradually strengthened capacity build-up in the MFA and other relevant institutions.
8 .3 Ensure capacity and attention in RBEC/BRC to support Romania in its transition from recipient to provider of ODA.
9 2.4 Continue a minimal UNDP presence in Romania to ensure proactive support and dialogue with national authorities in charge of development cooperation.
10 2.5 Create a triangular governance structure for the new partnership model: host government-local UNDP Presence - corporate UNDP (BERA/RBEC).
1. Recommendation: 1.1 End representational presence of UNDP in Romania by end 2012.
Management Response: [Added: 2012/07/30]

1.1International UNDP representation ends in December 2012, upon departure of RR a.i.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
International UNDP representation ends in December 2012, upon departure of RR a.i.
[Added: 2012/07/30] [Last Updated: 2013/12/10]
RBEC 2012/12 Completed
2. Recommendation: 1.2 Ensure minimal critical presence in CO Romania to ensure monitoring, trouble-shooting and direct line of communication to corporate UNDP (BERA, RBEC/BRC).
Management Response: [Added: 2012/07/30]

1.2 The transformation plan developed by the Senior UNDP CO management; it covers the 2013-2015 period and makes provision for critical UNDP staff to carry out the on-going initiatives and facilitate stakeholders dialogues especially with regard to sustainability and national ownership of the development results.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
The transformation plan 2013-2015 ensures that critical staff is in place to ensure implementation of on-going projects
[Added: 2012/07/30] [Last Updated: 2013/12/10]
UNDP project office 2013/01 Completed
3. Recommendation: 1.3 Increase visibility of CP in Romania by telling the success stories through beneficiaries to nurture national interest in and demand for international development cooperation as well as facilitate dialogue with the EU and traditional donors on possible ?new partnership models?.
Management Response: [Added: 2012/07/30]

1.3 One major event is being envisaged and planned for December 2012 in partnership with the Ministry of Foreign Affairs, with the objective of increasing the visibility of the UNDP Country Programme success stories. A brochure that will comprise at least one success story per UNDP CPAP outcome and a repository of all other CPAP projects will be publicly launched and presented at the event. One success story on Business Incubators has already been developed and included in the second edition of RBEC Development Success Stories and two more will be finalized soon. UNDP CO will select a consultant (proof reader and editor) to fine-tune the publication that will also be disseminated online.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
A major event is planned for Dec 2012 with the objective of increasing visibility of the UNDP CO achievements during the last CP and a UNDP success stories brochure will be produced and disseminated largely.
[Added: 2012/07/30] [Last Updated: 2013/12/10]
Romania UNDP CO 2015/06 Overdue-Initiated The difficulty in accomodating agendas and business schedules of the MFA partners have postponed this event
4. Recommendation: 1.4 Complete legal framework for completion of residual programme
Management Response: [Added: 2012/07/30]

1.4 The ?residual team? that oversees the implementation of the on-going projects will become operational, in accordance with the provisions of the transformation plan 2013-2015, which has been approved by UNDP HQ in July 2012.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
The residual team will become operational in accordance with the provision of the transformation plan.
[Added: 2012/07/30] [Last Updated: 2013/12/10]
Romania UNDP project office 2013/01 Completed
5. Recommendation: 1.5 Increase national ownership and coordination to ensure impact and sustainability of the CP. Ensure coordination with and among national implementing partners.
Management Response: [Added: 2012/07/30]

1.5 The UNDP ?residual team? will continue the implementation and progress towards achieving the development objectives of the on-going projects/programmes and will increase advocacy at the political level for a more visible national ownership of the projects? results.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
UNDP residual team will continue to facilitate institutional dialogue and advocacy for an increased national ownership of the joint initiatives.
[Added: 2012/07/30] [Last Updated: 2013/12/10]
Romanian UNDP project office 2015/06 Overdue-Initiated
6. Recommendation: Issue 2: Successor arrangement 2.12.1 Ensure political will and ownership/capacity in the MFA to reach sustainability of a national ODA structure by 2015
Management Response: [Added: 2012/07/30]

2.1. The New ODA Cooperation Partnership with Romania project for 2013-2015 has already been designed to further expand UNDP-MFA cooperation in the field of ODA and to consolidate MFA capacity. As such, the core objective of the project will be to strengthen the human resources of the MFA and to develop a sustainable national ODA structure by 2015. To this end, it is envisaged that a small Unit of Implementation will be set up to provide services to the MFA or on its behalf. UNDP will recruit the staff and provide training and overall management, with the expectation that in 2015, this unit will become part of the MFA or a nucleus of the Romanian ODA Agency. Moreover, in order to ensure ownership of project results, the MFA will participate in the management of the project in the roles of both Senior Supplier (in partnership with UNDP ? BRC) and Senior Beneficiary.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
The New ODA Cooperation Partnership with Romania project for 2013-2015 has already been designed to further expand UNDP-MFA cooperation in the field of ODA and to consolidate MFA capacity.
[Added: 2012/07/30] [Last Updated: 2013/12/10]
Romania MFA,, ODA project, BERA 2015/06 Overdue-Initiated
7. Recommendation: 2.2 Ensure a targeted and focused approach to Romanian development cooperation, going from simple to complex in consonance with the gradually strengthened capacity build-up in the MFA and other relevant institutions.
Management Response: [Added: 2012/07/30]

2.2. The New ODA Cooperation Partnership with Romania project for 2013-2015 will contribute to ensuring a targeted and focused approach to Romanian ODA, going from simple to complex as capacity is being build-up. Romania will continue to focus on existing ODA geographic and thematic priorities as per its national policy and legislation, but as its capacity develops, it is expected to gradually expand the scope fo its work. For instance, the project will support MFA to identify benchmark events (MDGs post 2015, Post-Busan forums, etc.) in which Romania?s experience and expertise can be presented. Deliverables that would earmark Romania?s contribution to global development cooperation efforts may include publications, reports, papers, and Romania-sponsored and/or hosted events.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
The New ODA Cooperation Partnership with Romania project for 2013-2015 will contribute to ensuring a targeted and focused approach to Romanian ODA
[Added: 2012/07/30] [Last Updated: 2013/12/10]
Romania MFA, ODA project, BERA 2015/06 Overdue-Initiated
8. Recommendation: .3 Ensure capacity and attention in RBEC/BRC to support Romania in its transition from recipient to provider of ODA.
Management Response: [Added: 2012/07/30]

2.3 The New ODA Cooperation Partnership with Romania project for 2013-2015 will focus on supporting the MFA to assume such a defined role through improved institutional capacity and awareness on ODA issues. The project is specifically designed to help develop Romania?s long term vision for development cooperation, and set up an effective system of managing ODA which can be integrated into the national planning and administration system.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
The New ODA Cooperation Partnership with Romania project for 2013-2015 will focus on supporting the MFA to assume such a defined role through improved institutional capacity and awareness on ODA issues. The start-up of this activity will commence in January 2013.
[Added: 2012/07/30] [Last Updated: 2013/12/10]
Romania MFA, ODA projects and BERA 2015/06 Overdue-Initiated
9. Recommendation: 2.4 Continue a minimal UNDP presence in Romania to ensure proactive support and dialogue with national authorities in charge of development cooperation.
Management Response: [Added: 2012/07/30]

2.4 The New ODA Cooperation Partnership with Romania project for 2013-2015 stipulates that a four-staff implementation unit will be based in Bucharest to ensure a permanent dialogue with the Romanian MFA and all other stakeholders in charge with development cooperation.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
The New ODA Cooperation Partnership with Romania project for 2013-2015 stipulates that a four-staff implementation unit will be based in Bucharest to ensure a permanent dialogue with the Romanian MFA
[Added: 2012/07/30] [Last Updated: 2013/12/10]
2013/03 Completed
10. Recommendation: 2.5 Create a triangular governance structure for the new partnership model: host government-local UNDP Presence - corporate UNDP (BERA/RBEC).
Management Response: [Added: 2012/07/30]

2.5 The above mentioned unit will work under the joint supervision of BRC/RBEC and the country office. The association of the BERA Adviser on Emerging Donors, based in BRC, will contribute to the coordination of CO and BRC efforts with corporate UNDP ( RBEC and BERA).

Key Actions:

Key Action Responsible DueDate Status Comments Documents
The above mentioned unit will work under the joint supervision of BRC/RBEC and the country office.
[Added: 2012/07/30] [Last Updated: 2013/12/10]
ODA Project , RBEC, BERA 2013/03 Completed