- Evaluation Plan:
- 2008-2012, Malaysia
- Evaluation Type:
- Mid Term Project
- Planned End Date:
- 01/2010
- Completion Date:
- 11/2009
- Status:
- Completed
- Management Response:
- Yes
- Evaluation Budget(US $):
- 30,000
»
Malaysia »
2008-2012 »
Conservation of Biological Diversity through Improved Forest Planning Tools
Conservation of Biological Diversity through Improved Forest Planning Tools
Share
Document | Type | Language | Size | Status | Downloads |
---|---|---|---|---|---|
![]() |
report | English | 534.14 KB | Posted | 1095 |
Title | Conservation of Biological Diversity through Improved Forest Planning Tools | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Atlas Project Number: | 00051228 | ||||||||||
Evaluation Plan: | 2008-2012, Malaysia | ||||||||||
Evaluation Type: | Mid Term Project | ||||||||||
Status: | Completed | ||||||||||
Completion Date: | 11/2009 | ||||||||||
Planned End Date: | 01/2010 | ||||||||||
Management Response: | Yes | ||||||||||
Focus Area: |
|
||||||||||
Corporate Outcome and Output (UNDP Strategic Plan 2018-2021) |
|
||||||||||
Evaluation Budget(US $): | 30,000 | ||||||||||
Source of Funding: | GEF | ||||||||||
Joint Programme: | No | ||||||||||
Joint Evaluation: | No | ||||||||||
Evaluation Team members: |
|
||||||||||
GEF Evaluation: | Yes
|
||||||||||
Key Stakeholders: | Forest Research Institute of Malaysia (FRIM) | ||||||||||
Countries: | MALAYSIA |
Lessons | |
---|---|
Findings |
Recommendations | |
---|---|
1 | Incentives for improved forest management are insufficient for commercial operations. The Malaysian government (State and National) should ask FRIM to work with them to review ways they can encourage and facilitate good forestry practices (e.g. tax breaks etc). |
Key Action Update History
Loading..
1. Recommendation: Incentives for improved forest management are insufficient for commercial operations. The
Malaysian government (State and National) should ask FRIM to work with them to review
ways they can encourage and facilitate good forestry practices (e.g. tax breaks etc).
Management Response: [Added: 2011/12/28]
The issue shall be discussed further in the NSC. Further detail meetings need to eb organized between the states and the federal government.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
National planning process
[Added: 2011/12/28] [Last Updated: 2012/01/09] |
MNRE, FRIM, Perak State government | 2012/01 | Completed | discussions done. |