Evaluation of Partners for Prevention Regional Joint Programme for Gender-based Violence Prevention in Asia and the Pacific 2008 till 2012

Report Cover Image
Evaluation Plan:
2011-2014, UNV
Evaluation Type:
Final Project
Planned End Date:
05/2013
Completion Date:
05/2013
Status:
Completed
Management Response:
Yes
Evaluation Budget(US $):
10,000

Share

Document Type Language Size Status Downloads
Download document p4p_evaluation_report.pdf report English 1726.01 KB Posted 631
Download document Management response to the evaluation of the P4P programme_20 June.pdf related-document English 426.02 KB Posted 463
Title Evaluation of Partners for Prevention Regional Joint Programme for Gender-based Violence Prevention in Asia and the Pacific 2008 till 2012
Atlas Project Number:
Evaluation Plan: 2011-2014, UNV
Evaluation Type: Final Project
Status: Completed
Completion Date: 05/2013
Planned End Date: 05/2013
Management Response: Yes
Focus Area:
  • 1. Cross-cutting Development Issue
Corporate Outcome and Output (UNDP Strategic Plan 2014-2017)
  • 1. UNDP programmes/projects integrate gender equality and women's empowerment in line with the UNDP gender equality strategy, 2008-2011
Evaluation Budget(US $): 10,000
Source of Funding:
Joint Programme: No
Mandatory Evaluation: Yes
Joint Evaluation: Yes
Evaluation Team members:
Name Title Email Nationality
Frank Noij
Nadine Jubb
Jan Reynders
GEF Evaluation: No
Key Stakeholders:
Location of Evaluation: Country Level
Countries: ETHIOPIA
Lessons
Findings
Recommendations
1 Evaluation recommendation 1. 1. Use the remainder of 2013 to finish what was started and to realise the outputs of the extended first phase of the P4P programme
2 Evaluation recommendation 2: 2. Prepare for a second programme phase of P4P with a focus on GBV prevention, transforming harmful masculinities and engaging men and boys, making use of full programme and policy cycles to test the TOC of P4P.
3 Evaluation recommendation 3: 3. Implement a second phase of the P4P programme, translating the outputs of the first phase into new policies and programmes that are owned in-country and that can be expected to be sustainable. This will optimise the investments made so far. This approach will require a four-year time frame.
4 Evaluation recommendation 4: 4. Practicing and supporting Results-Based Management
5 Evaluation recommendation 5: 5. Enhance coordination at the regional and country levels
6 Evaluation recommendation 6: 6. Regional joint programme modality for the second phase of P4P
7 Evaluation recommendation 7: 7. Strengthen joint programme governance
8 Evaluation recommendation 8: 8. Enhance joint programme management
9 Evaluation recommendation 9: 9. Develop a resource mobilization strategy
1. Recommendation: Evaluation recommendation 1. 1. Use the remainder of 2013 to finish what was started and to realise the outputs of the extended first phase of the P4P programme
Management Response: [Added: 2014/01/16]

Relevant and partially acceptable.

Key Actions:

2. Recommendation: Evaluation recommendation 2: 2. Prepare for a second programme phase of P4P with a focus on GBV prevention, transforming harmful masculinities and engaging men and boys, making use of full programme and policy cycles to test the TOC of P4P.
Management Response: [Added: 2014/01/16]

Relevant and partially acceptable.

Key Actions:

3. Recommendation: Evaluation recommendation 3: 3. Implement a second phase of the P4P programme, translating the outputs of the first phase into new policies and programmes that are owned in-country and that can be expected to be sustainable. This will optimise the investments made so far. This approach will require a four-year time frame.
Management Response: [Added: 2014/01/16]

Relevant and acceptable.

Key Actions:

4. Recommendation: Evaluation recommendation 4: 4. Practicing and supporting Results-Based Management
Management Response: [Added: 2014/01/16]

Relevant and acceptable.

Key Actions:

5. Recommendation: Evaluation recommendation 5: 5. Enhance coordination at the regional and country levels
Management Response: [Added: 2014/01/16]

Relevant and acceptable.

Key Actions:

6. Recommendation: Evaluation recommendation 6: 6. Regional joint programme modality for the second phase of P4P
Management Response: [Added: 2014/01/16]

Relevant and acceptable.

Key Actions:

7. Recommendation: Evaluation recommendation 7: 7. Strengthen joint programme governance
Management Response: [Added: 2014/01/16]

Relevant and partially acceptable.

Key Actions:

8. Recommendation: Evaluation recommendation 8: 8. Enhance joint programme management
Management Response: [Added: 2014/01/16]

Relevant and partially acceptable.

Key Actions:

9. Recommendation: Evaluation recommendation 9: 9. Develop a resource mobilization strategy
Management Response: [Added: 2014/01/16]

Relevant and acceptable.

Key Actions: