Mid-term evaluation of the Support to the Nigerian Electoral Cycle 2012-2015

Report Cover Image
Evaluation Plan:
2014-2017, Nigeria
Evaluation Type:
Mid Term Project
Planned End Date:
07/2014
Completion Date:
07/2014
Status:
Completed
Management Response:
Yes
Evaluation Budget(US $):
40,000

Share

Document Type Language Size Status Downloads
Download document DGDII_Evaluation_Report_Final.pdf report English 2207.79 KB Posted 852
Title Mid-term evaluation of the Support to the Nigerian Electoral Cycle 2012-2015
Atlas Project Number:
Evaluation Plan: 2014-2017, Nigeria
Evaluation Type: Mid Term Project
Status: Completed
Completion Date: 07/2014
Planned End Date: 07/2014
Management Response: Yes
Corporate Outcome and Output (UNDP Strategic Plan 2014-2017)
  • 1. Output 2.1. Parliaments, constitution making bodies and electoral institutions enabled to perform core functions for improved accountability, participation and representation, including for peaceful transitions
Evaluation Budget(US $): 40,000
Source of Funding: EU
Joint Programme: No
Mandatory Evaluation: Yes
Joint Evaluation: No
Evaluation Team members:
Name Title Email Nationality
Charlemagne GĂ“MEZ
Heinz JOCKERS
GEF Evaluation: No
Key Stakeholders: UNDP, EU, DFID, CIDA, INEC, CSOs
Countries: NIGERIA
Comments: This evaluation has been commissioned by the EU, in line with its funding of the DGD multi-funded project
Lessons
Findings
Recommendations
1 Ensure that Risk Management is strengthened and coordinated with key stakeholders to the process
2 Create a Strategic Thematic Group on Voter Education led by INEC
3 Strengthen collaboration and coordination between other international partners and the Project DGD
4 Ensure that the website is consistently updated
1. Recommendation: Ensure that Risk Management is strengthened and coordinated with key stakeholders to the process
Management Response: [Added: 2016/01/13]

DGD to develop a risk management tracking mechanism. . In close coordination with other entities with a solid background in security and knowledge of the country, the DGD will conduct contextual analysis of the risk levels. This will be helpful in fine-tuning project strategies for interventions at State and LGA levels.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Conduct Election contextual risk analysis in 19 states
[Added: 2016/01/13]
DGD/International partners/NISER 2015/05 Overdue-Initiated Process completed
Coordination with Election security/Conflict analysis initiatives in the choice of focal states to strengthen risk management.
[Added: 2016/01/13]
DGD/International partners/NISER 2015/05 Completed Done
2. Recommendation: Create a Strategic Thematic Group on Voter Education led by INEC
Management Response: [Added: 2016/01/13]

A National Inter-Agency Advisory Committee on Voter Education and Publicity will be established, led by INEC and the Media, Civil Society, Inter-faith groups, traditional leaders and the National Orientation Agency as members of the Advisory Committee . The members will pool resources together in order to compliment activities and to have maximum voter education outreach.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
A retreat to get NICVEP off the ground was supported.
[Added: 2016/01/13]
INEC/DGD/Media/CSos/NOA 2015/04 Overdue-Initiated Process completed
Technical and financial assistance was provided to INEC to develop VE initiatives and coordinate voter education outreaches at national and states levels.
[Added: 2016/01/13]
INEC/DGD/Media/CSos/NOA 2015/04 Completed Done
3. Recommendation: Strengthen collaboration and coordination between other international partners and the Project DGD
Management Response: [Added: 2016/01/13]

DGD to actively continue reaching out to and contribute to bi-lateral and multi-lateral meetings with other international partners in the lead up to the 2015 general elections to ensure coordination and collaboration in all project activities. Responsible Due Date

Key Actions:

Key Action Responsible DueDate Status Comments Documents
DGD was actively represented in coordination platforms including the Elections Coordination Group, Voter Education Coordination group, and the DDiN2 Implementing partners meetings. Bi-lateral discussions were held with IFES to ensure maximum coordination and avoid duplication.
[Added: 2016/01/13]
DGD/International partners. 2015/12 Overdue-Initiated Significant progress has been made
4. Recommendation: Ensure that the website is consistently updated
Management Response: [Added: 2016/01/13]

DGD to continuously update its web page to reflect the plethora of activities that have taken place in the elections phase. Progress is on, in coordination with the UNDP Communications team to enhance the web page as a useful tool for promoting project results.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Communications consultant recruited and on board during the elections phase to develop web stories from project outcomes
[Added: 2016/01/13]
UNDP/DGD 2015/12 Completed Accomplished