Title Promoting the use of electric water pumps for irrigation in Sudan
Atlas Project Number: 00094271
Evaluation Plan: 2018-2021, Sudan
Evaluation Type: Mid Term Project
Status: Completed
Completion Date: 12/2018
Planned End Date: 07/2018
Management Response: Yes
Focus Area:
  • 1. Poverty and MDG
  • 2. Environment & Sustainable Development
  • 3. Cross-cutting Development Issue
  • 4. Others
Corporate Outcome and Output (UNDP Strategic Plan 2014-2017)
  • 1. Output 1.5. Inclusive and sustainable solutions adopted to achieve increased energy efficiency and universal modern energy access (especially off-grid sources of renewable energy)
Evaluation Budget(US $): 40,000
Source of Funding: GEF
Evaluation Expenditure(US $): 25,617
Joint Programme: No
Joint Evaluation: No
Evaluation Team members:
Name Title Email Nationality
Ron Mukanya Initernational Consultant ronald.mukanya@gmail.com
Babiker Abdalla Ibrahim National Consultant babdalla.ibrahim@gmail.com
GEF Evaluation: Yes
GEF Project Title: Promoting the use of electric water pumps for irrigation in Sudan
Evaluation Type: Mid-term Review
Focal Area: Climate Change
Project Type: FSP
GEF Phase: GEF-5
GEF Project ID: 5673
PIMS Number: 5324
Key Stakeholders: UNDP, GEF, Ministry of water and natural resources, MIC
Countries: SUDAN
Comments:

UNDP, GEF, Ministry of water and natural resources, MIC

Lessons
Findings
Recommendations
1

The MTR of PEWP has identified a number of issues that are presented below as recommendations per outcome for use in the project design going forward and implementation of similar projects in future.

Outcome 1: Financing and dissemination mechanism established and operational to support a PV pump installation programme

1. Recommendation:

The MTR of PEWP has identified a number of issues that are presented below as recommendations per outcome for use in the project design going forward and implementation of similar projects in future.

Outcome 1: Financing and dissemination mechanism established and operational to support a PV pump installation programme

Management Response: [Added: 2018/11/28]

Financing and dissemination mechanism established and operational to support a PV pump installation programme

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Establish a mechanism to support a PV pump installation programme. 1. UNDP prepare concept note for the PV Fund 2. UNDP conduct brainstorming workshop for PV fund.
[Added: 2018/11/28] [Last Updated: 2018/12/10]
UNDP & Ministry of Water Resources Irrigation and Electricity 2018/12 Completed Draft management response plan, waiting for the final management response plan by the project board members expected before the end of 2018.. History