- Evaluation Plan:
- 2018-2022, Sudan
- Evaluation Type:
- Mid Term Project
- Planned End Date:
- 07/2018
- Completion Date:
- 12/2018
- Status:
- Completed
- Management Response:
- Yes
- Evaluation Budget(US $):
- 40,000
Promoting the use of electric water pumps for irrigation in Sudan
Share
Document | Type | Language | Size | Status | Downloads |
---|---|---|---|---|---|
![]() |
tor | English | 525.83 KB | Posted | 1263 |
![]() |
report | English | 1322.61 KB | Posted | 1629 |
Title | Promoting the use of electric water pumps for irrigation in Sudan | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Atlas Project Number: | 00094271 | ||||||||||||||
Evaluation Plan: | 2018-2022, Sudan | ||||||||||||||
Evaluation Type: | Mid Term Project | ||||||||||||||
Status: | Completed | ||||||||||||||
Completion Date: | 12/2018 | ||||||||||||||
Planned End Date: | 07/2018 | ||||||||||||||
Management Response: | Yes | ||||||||||||||
Focus Area: |
|
||||||||||||||
Corporate Outcome and Output (UNDP Strategic Plan 2018-2021) |
|
||||||||||||||
Evaluation Budget(US $): | 40,000 | ||||||||||||||
Source of Funding: | GEF | ||||||||||||||
Evaluation Expenditure(US $): | 25,617 | ||||||||||||||
Joint Programme: | No | ||||||||||||||
Joint Evaluation: | No | ||||||||||||||
Evaluation Team members: |
|
||||||||||||||
GEF Evaluation: | Yes
|
||||||||||||||
Key Stakeholders: | UNDP, GEF, Ministry of water and natural resources, MIC | ||||||||||||||
Countries: | SUDAN | ||||||||||||||
Comments: | UNDP, GEF, Ministry of water and natural resources, MIC |
Lessons | |
---|---|
Findings |
Recommendations | |
---|---|
1 | The MTR of PEWP has identified a number of issues that are presented below as recommendations per outcome for use in the project design going forward and implementation of similar projects in future. Outcome 1: Financing and dissemination mechanism established and operational to support a PV pump installation programme |
Key Action Update History
The MTR of PEWP has identified a number of issues that are presented below as recommendations per outcome for use in the project design going forward and implementation of similar projects in future.
Outcome 1: Financing and dissemination mechanism established and operational to support a PV pump installation programme
Management Response: [Added: 2018/11/28]
Financing and dissemination mechanism established and operational to support a PV pump installation programme
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Establish a mechanism to support a PV pump installation programme.
1. UNDP prepare concept note for the PV Fund
2. UNDP conduct brainstorming workshop for PV fund.
[Added: 2018/11/28] [Last Updated: 2018/12/10] |
UNDP & Ministry of Water Resources Irrigation and Electricity | 2018/12 | Completed | Draft management response plan, waiting for the final management response plan by the project board members expected before the end of 2018.. History |