Mid-term Evaluation of Niger Delta Biodiversity Conservation Project
Share
Document | Type | Language | Size | Status | Downloads |
---|---|---|---|---|---|
![]() |
tor | English | 70.84 KB | Posted | 1310 |
![]() |
report | English | 1099.70 KB | Posted | 2470 |
Title | Mid-term Evaluation of Niger Delta Biodiversity Conservation Project | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Atlas Project Number: | 00061066 | ||||||||||||||
Evaluation Plan: | 2018-2022, Nigeria | ||||||||||||||
Evaluation Type: | Mid Term Project | ||||||||||||||
Status: | Completed | ||||||||||||||
Completion Date: | 02/2018 | ||||||||||||||
Planned End Date: | 08/2018 | ||||||||||||||
Management Response: | Yes | ||||||||||||||
Focus Area: |
|
||||||||||||||
Corporate Outcome and Output (UNDP Strategic Plan 2018-2021) |
|
||||||||||||||
SDG Goal |
|
||||||||||||||
SDG Target |
|
||||||||||||||
Evaluation Budget(US $): | 20,000 | ||||||||||||||
Source of Funding: | |||||||||||||||
Evaluation Expenditure(US $): | 50,000 | ||||||||||||||
Joint Programme: | No | ||||||||||||||
Joint Evaluation: | No | ||||||||||||||
Evaluation Team members: |
|
||||||||||||||
GEF Evaluation: | Yes
|
||||||||||||||
Key Stakeholders: | Federal Ministry of Environment | ||||||||||||||
Countries: | NIGERIA |
Lessons | |
---|---|
Findings |
Recommendations | |
---|---|
1 | UNDP lead a process of revising the project strategy, to focus the project on further work on the CBAPs. |
2 | UNDP needs to strengthen its technical support to the project. |
3 | The project should engage civil society groups with skills and experiences on participatory biodiversity conservation planning and implementation. |
Key Action Update History
UNDP lead a process of revising the project strategy, to focus the project on further work on the CBAPs.
Management Response: [Added: 2018/08/06]
Recommendation accepted
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Engage a consultant to undertake the review of programme strategy to refocus on CBAPs implementation
[Added: 2018/08/06] [Last Updated: 2021/10/15] |
UNDP, Federal Ministry of Environment, Project Steering Committee (PSC), State focal persons | 2018/11 | Completed | Consultant was engaged and liaised with communities in the Niger Delta region History |
UNDP needs to strengthen its technical support to the project.
Management Response: [Added: 2018/08/06]
Recommendation accepted
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Restructure PMU to include National expert on community engagement to implement changes to the programme strategy
[Added: 2018/08/06] [Last Updated: 2021/10/15] |
UNDP/ PMU | 2018/11 | Completed | National expert recruited History |
The project should engage civil society groups with skills and experiences on participatory biodiversity conservation planning and implementation.
Management Response: [Added: 2018/08/06]
Recommendation accepted
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
16.1 Develop criteria for joint identification and selection of civil society organizations in the Niger Delta
[Added: 2018/08/06] [Last Updated: 2021/10/15] |
PMU/ Federal Ministry of Environment / States and communities | 2018/12 | Completed | Criteria developed History |