1. Recommendation:
  1.  Complete EWS training on the next project by:
  • providing flood forecast training after the multimodal software (ACMAD and MyDEWETRA:  weather and hydrological forecasting tools) is operational after its design phase. This is a follow-up to CIMA-trained IGEBU experts responsible for analyzing and producing weather reports;
  • ensuring the maintenance of the hydrological stations by purchasing sensors as some of them have been worn out;
  • putting into place a contingency plan for the EWS by conducting simulation exercises; and
  • training EWS focal points on the effectives use of the EWS communication tools at IGEBU. This would mean that EWS communication tools should be distributed to the EWS focal points and the emergency management and decision-making team in the field.
Management Response: [Added: 2021/09/17] [Last Updated: 2021/12/06]

Accepted 

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Providing flood forecast training after the multimodal software (ACMAD and MyDEWETRA: weather and hydrological forecasting tools) is operational after its design phase. This is a follow-up to CIMA-trained IGEBU experts responsible for analysing and producing weather reports.
[Added: 2021/12/28]
ACMAD/PNUD 2020/10 Completed Done from May to September continue and operatizing the system
Ensuring the maintenance of the hydrological stations by purchasing sensors as some of them have been worn out.
[Added: 2021/12/28]
Marie Ange 2020/11 Completed The training has been conducted for 2 weeks and the hydro meteorologist were trained in Flood forecast and Hydrological Modelling and the flood or hydrological model is available on MyDEWETRA Platform
Putting into place a contingency plan for the EWS by conducting simulation exercises.
[Added: 2021/12/28]
Marie Ange Kigeme 2020/12 Completed Realized 2021A contingency plan for the EWS functioning ACMAD has put in place a setup backup and regularly follow up with IGEBU Technicians on EWS Enhancing the undergoing EWS using the existing technical capacities at Red Cross Burundi, National Plate form body. ACMAD continue providing maintenance support and weather stations
Training EWS focal points on the effectives use of the EWS communication tools at IGEBU. This would mean that EWS communication tools should be distributed to the EWS focal points and the emergency management and decision-making team in the field
[Added: 2021/12/28]
Red Cross Burundi /UNDP 2021/12 Completed Members of the National Plate form and the Focal Points are trained and are able to set up a Community-based Early Warning System to prevent the risks of disasters linked to climate change Red Cross provided capacities to focal points among communities in the project areas and conducted simulation exercise with them
2. Recommendation:

Improve the technical capacities of institutions (i.e. IGEBU, provincial governments, communal services and local communities) to manage the mapping of climate-induced flood and erosion risks along the Ntahangwa watershed.

Management Response: [Added: 2021/09/17]

Accepted

Key Actions:

Key Action Responsible DueDate Status Comments Documents
UNDP would collaborate with other partners in the EWS such is OIM, WB which are involved in hydrological modelling to map out climate-sensitive flood and erosion risks at national level and make use of their data
[Added: 2021/12/28]
UNDP and Government of Burundi 2023/12 Initiated
UNDP in collaboration with Ministry of Environment will put in place an integrated watershed management plan to provide an understanding of the key areas in the watershed for the provision of ecosystem services for flood and erosion control and to guide the development and rehabilitation of the Ntahangwa watershed and erosion control;
[Added: 2021/12/28]
UNDP and Government of Burundi 2023/12 Initiated
ACMAD and CIMA explored the integration of other hazards (Drought monitoring; Soil Erosions and landslide) in MyDWETRA Tool
[Added: 2021/12/28]
ACMAD, CIMA with financial support World Bank Project on land restoration 2023/12 Initiated
ACMAD trained Burundi Red Cross and Civil Protection on the use of the MyDEWETRA and interpretation of the Weather and Climate Information
[Added: 2021/12/28]
ACMAD and CIMA 2020/12 Completed ACMAD and CIMA Conducted training on the use and interpretation of bulletins, Credentials (Username and password) have been provided to Burundi RedCross and Civil Protection of Burundi
3. Recommendation:

Establish an investment program that carries on the work of CDRM Project on the Ntahangwa watershed

Management Response: [Added: 2021/09/17]

Accepted

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Ministry of Environment shall build synergy with donors’ community intervening around Ntahangwa river
[Added: 2021/12/28]
MINEAGRIE/UNDP 2023/12 Not Initiated
Ministry in collaboration of UNDP to put in place coordination mechanisms for watershed management
[Added: 2021/12/28]
UNDP 2023/12 Not Initiated
4. Recommendation:

Continue with investment programs to promote livelihood resilience and green entrepreneurship.

Management Response: [Added: 2021/09/17]

Accepted

Key Actions:

Key Action Responsible DueDate Status Comments Documents
To ensure the resource mobilisation
[Added: 2021/12/28]
UNDP/ MINEAGRIE 2023/12 Not Initiated
stakeholders’ consultations
[Added: 2021/12/28]
UNDP/ MINEAGRIE 2022/12 Not Initiated
5. Recommendation:

For subsequent projects to CDRM, step up safeguard-related requirements as per UNDP’s latest guidance to ensure that sufficient resources are allocated to conduct this work

Management Response: [Added: 2021/09/17] [Last Updated: 2021/12/06]

Accepted

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Recruitment of environmental officer
[Added: 2021/12/28]
UNDP 2023/12 Not Initiated
6. Recommendation:

Engage with the GoB to enforce co-financing commitments

Management Response: [Added: 2021/12/06]

Acceptée 

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Lobbying with ministry of Finance for Government contribution
[Added: 2021/12/28]
MINEAGRIE 2023/12 Not Initiated
Advocacy for donor’s community to invest jointly in environmental issues and watershed management
[Added: 2021/12/28]
MINEAGRIE/ UNDP 2023/12 Not Initiated
7. Recommendation:

For subsequent projects to CDRM, prepare a PRF with SMART indicators with an economy of words.

Management Response: [Added: 2021/12/06]

Acceptée 

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Involved M&E colleagues in designing project Indicators
[Added: 2021/12/28]
UNDP/ Marie ANge 2022/12 Not Initiated
Build capacity on how to set SMART indicators during project development
[Added: 2021/12/28]
Unit M&E UNDP 2022/12 Not Initiated

Latest Evaluations