Evaluation of the Outcome 5.2: Access to sustainable energy improved through increased electricity production by using indigenous renewable energy resources, improved energy efficienct and the development of Georgia's Energy Corridor
Commissioning Unit: Georgia
Evaluation Plan: 2007-2008
Evaluation Type: Outcome
Completion Date: 06/2008
Unit Responsible for providing Management Response: Georgia
Documents Related to overall Management Response:
 
1. Recommendation: Given the dearth of energy efficiency activities in Georgia, UNDP can start with creating awareness on energy efficiency, especially at decision-makers level, which can be followed by more larger-scale activities focusing on the public-at-large
Management Response: [Added: 2009/01/27]

UNDP will take into consideration the evaluators' recommendations in both current program and the new program to be developed in 2009

Key Actions:

Key Action Responsible DueDate Status Comments Documents
UNDP will intensify a dialogue with decision-makers on renewable energy and energy efficinecy issues under the UNDP-GEF renewable energy project as well as start identification of a new energy efficiency project. In addition, UNDP will integrate energy efficiency measures in its new programme covering 2011-2014
[Added: 2009/01/27] [Last Updated: 2011/12/29]
UNDP, UNDP-GEF project management 2011/12 Completed UNDP has recently started a new GEF-funded project on using biomass for energy efficiency. This project is implemented in close partnership with Tbilisi Municipality. Besides, negotiations are on about new project on energy efficiency in residential buildings.
2. Recommendation: In renewable energy the current privatization drive should be supplemented in such a way that not only a few large oligopolistic power producers profit, but smaller-scale independent power producers in the rural areas as well. If offered some preferential tariffs, small-scale hydropower producers (SHPPs) and renewable energy producers in general, can compete and having the development dividend in terms of creating income in more remote rural areas. This will first of all require convincing policy and decision-makers as well as providing technical support in the formulation and implementation of projects, aided by appropriate financing schemes.
Management Response: [Added: 2009/01/27]

Under UNDP-GEF renewable energy project UNDP will put a greater emphasis on a dialogue with the policy-makers and continue building up project pipelines for existing financial mechanisms, e.g. Renewable Energy Fund and EBRD Energy Efficiency Facility

Key Actions:

Key Action Responsible DueDate Status Comments Documents
UNDP will revise renewable energy project to focus in a greater scale on policy dialogue and to expand the TA for renewable energy fulll project development cycle
[Added: 2009/01/27] [Last Updated: 2011/12/29]
UNDP, UNDP-GEF project management 2011/12 Completed Project was revised according to the reccomendations made. UNDP together with KfW has supported setting up of a Renewable Energy Fund which provided financial support for contruction and reconstruction of SHPPs. Besides, TA provided by UNDP was instrumental for the RE Fund and partner banks in making their decisions about funding construction of SHPPs.
3. Recommendation: Regarding rural energy, the promotion of energy saving technologies in rural areas, such as solar water heaters and efficient stoves should be further promoted. This will require an appropriate rural energy supply policy that finds a balance between supporting the poorer segments of the rural populace and financial sustainability
Management Response: [Added: 2009/01/27]

UNDP will prepare a large-scale project to expand rural energy program from pilot regions to other rural areas and will make afforts to mobilize resources

Key Actions:

Key Action Responsible DueDate Status Comments Documents
UNDP will prepare a large-scale program on micro-size renewable energy and energy efficient technologies and present to various donors for resource mobilization
[Added: 2009/01/27]
UNDP No due date No deadline established UNDP has prepared USD 2.5 million project proposal on household level renewable energy and energy efficient technologies and together with pilot project results presented to donors. Although, UNDP was unable to mobilize resources for this project, donors expressed their readiness to work in this area. For instance, BP has launched an energy bus initiative that links aggressive public awareness to micro credit program. The program is supported by USAID, OSCE and EBRD. In 2009 UNDP will continue looking for a donor to fund rural energy project