Commissioning Unit: | Mozambique |
---|---|
Evaluation Plan: | 2007-2009 |
Evaluation Type: | Project |
Completion Date: | 01/2009 |
Unit Responsible for providing Management Response: | Mozambique
|
Documents Related to overall Management Response: |
|
Key Action Update History
Management Response: [Added: 2010/02/22] [Last Updated: 2010/02/22]
The UIP and UNDP will continue to analyze the links between poverty and access to Justice and feed this information for the project design for phase II. Already these linkages were reviewed in the PACAJ study on gender issues in the administration of Justice and Police done by the CFJJ with project funds.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
1.1. Analysis to be part of the phase II design.
[Added: 2010/02/22] [Last Updated: 2013/09/27] |
UIP/Governance Unit | 2010/12 | Completed | Activity for 2010 AWP |
Management Response: [Added: 2010/02/22] [Last Updated: 2010/02/22]
The study on Human Rights Perception in Mozambique touched upon this issue. However, the design team for phase II will be mandated to review those obstacles in light with the construction of the Palaces of Justice at district level done by the pilot project.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
2.1. Design a team to review statistics from district tribunals since the pilot project started, and monitor district tribunal functioning and its impact on access to justice.
[Added: 2010/02/22] |
UIP/Governance Unit | 2010/12 | Overdue-Not Initiated |
Management Response: [Added: 2010/02/22] [Last Updated: 2010/02/22]
One of the activities of the bridging project in 2010 will aim at supporting the development of a monitoring system for the functioning of the Palaces of Justice built by the pilot project.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
3.1. Assess the functioning of the Palaces of Justice in pilot districts of the PACAJ.
[Added: 2010/02/22] [Last Updated: 2013/09/27] |
UIP/Governance Unit | 2010/12 | Completed | Activity for 2010 |
Management Response: [Added: 2010/02/22] [Last Updated: 2010/02/22]
The President and the AGO have endorsed the philosophy of the Palaces of Justice. The expansion is already foreseen in the PEI for the Justice Sector.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
4.1. Ensure coordination between other justice stakeholders and donors involved in the Justice sector for consolidated approach and efficiency of the Palaces.
[Added: 2010/02/22] [Last Updated: 2013/09/27] |
UIP/Governance Unit | 2010/12 | Completed |
Management Response: [Added: 2010/02/22] [Last Updated: 2010/02/22]
This recommendation is in line with the Government programme aiming towards more decentralization. The ?PARPA II?, PEI, UNDAF, CPAP should all lead towards a phase II project that also goes in this direction.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
5.1. To support provincial and district commissions for legal control .
5.2. To encourage the expansion and strengthening of the district level commissions for legal control.
[Added: 2010/02/22] [Last Updated: 2013/09/27] |
UIP/Governance Unit | 2010/12 | Completed | Activity for 2010 AWP |
Management Response: [Added: 2010/02/22] [Last Updated: 2010/02/22]
During implementation, PACAJ has undergone two surveys on knowledge management at district and provincial levels to assess opinion and capacity of stakeholders in the justice sector. NGOs and local radios have been working on legal awareness. IPAJ has developed TV programmes on legal awareness. Assessment of justice capacities should be done following pilot project activities.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
6.1. Undertake local level capacity assessment of justice providers.
[Added: 2010/02/22] |
UIP/Governance Unit | 2010/12 | Overdue-Not Initiated | Activity for 2010 AWP |
Management Response: [Added: 2010/02/22] [Last Updated: 2010/02/22]
The coordinating meetings should continue at central, provincial, and district levels to foster efficiency in justice delivery.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
7.1. Immediate Action Plan (PAI) methodology to be used to monitor 2010 AWP implementation.
[Added: 2010/02/22] |
UIP | 2010/12 | Overdue-Initiated | ||
7.2. Coordination meetings to be conducted regularly.
[Added: 2010/02/22] [Last Updated: 2013/09/27] |
UIP | 2010/12 | Completed | Activity for 2010 AWP |
Management Response: [Added: 2010/02/22] [Last Updated: 2010/02/22]
We agree with the recommendation and suggest doing both capacity building of CSOs and using them for activity implementation. Experience demonstrated low capacity in CSOs, especially at local level. Future project should contemplate training in financial management and RBM. Next project should plan for high maintenance activities with CSOs.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
8.1. Design a team to review impact of the awareness campaign and legal assistance in the province prior to elaborate project document.
[Added: 2010/02/22] |
UIP/Governance Unit | 2010/12 | Overdue-Not Initiated | Activity for 2010 AWP |
Management Response: [Added: 2010/02/22] [Last Updated: 2010/02/22]
District and provincial Commissions for legality control should be empowered to monitor and facilitate the functioning of the penal justice.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
9.2. To continue support commissions via provincial offices.
[Added: 2010/02/22] |
UIP/Governancne Unit | 2007/01 | Overdue-Initiated | Activity for 2010 AWP | |
9.1. To design a team to build in their capacity assessment monitoring capabilities.
[Added: 2010/02/22] |
UIP/Governancne Unit | 2010/12 | Overdue-Not Initiated | Activity for 2010 AWP |
Management Response: [Added: 2010/02/22]
Legislative revisions in prison reform and alternative to imprisonment should be done in coordination with the Parliament to ensure effectiveness of policy reforms.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
10.1. To foster coordination between the UNDP, the Parliament, and the Justice Project in the development of legislation revisions.
[Added: 2010/02/22] [Last Updated: 2013/09/27] |
Governance Unit | 2010/12 | Completed | Activity for 2010 AWP |
Management Response: [Added: 2010/02/22]
Institutional diagnostics and strategic plan were done during the PACAJ. They should inform the design of the next phase and possible policy reviews.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
11.1. Design a team to use strategic plans and institutional diagnostics to help develop the next phase of the Justice Project.
[Added: 2010/02/22] |
UIP/Governance Unit | 2010/12 | Overdue-Not Initiated | Activity for 2010 AWP | |
11.2. Promote further policy/legislative necessary reforms after DGTTF prison legal reform and alternative to imprisonment in order to ensure integral legal framework for the prison system.
[Added: 2010/02/22] |
UIP/Governance Unit | 2010/12 | Overdue-Not Initiated | Designing a team is currently being dealt with |
Management Response: [Added: 2010/02/22]
A continuation of the monitoring framework was developed during the PACAJ to acompany policy and activity implementation.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
12.1. To transfer knowledge and tools to the Ministry of Justice to monitor justice policy and activities.
[Added: 2010/02/22] |
UIP/Governance Unit | 2010/12 | Overdue-Initiated |
Management Response: [Added: 2010/02/22]
The PAI methodology should be used, and provincial offices should be maintained to foster efficiency and good functioning of sub-commissions at district level.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
13.1. To monitor the functioning of sub-commissions at district level and disseminate the PAI methodology at local level.
[Added: 2010/02/22] |
UIP/Governance Unit | 2010/12 | Overdue-Initiated |
Management Response: [Added: 2010/02/22]
The use of the community radio should continue, and the IPAJ should pursue its awareness campaign.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
14.1 To support the IPAJ legal awareness campaign in TV.
[Added: 2010/02/22] [Last Updated: 2013/09/27] |
UIP/Governance Unit | 2010/12 | Completed | Five TV programmes have been already produced | |
14.2 To expand legal awareness with the IPAJ booklets and radio programme.
[Added: 2010/02/22] |
UIP/Governance Unit | 2010/12 | Overdue-Not Initiated | Activity for 2010 AWP |
Management Response: [Added: 2010/02/22]
Legal awareness should be streamlined and lead by the IPAJ. A paralegal manual should be developed and shared with the IPAJ partners working in the area of legal awareness and legal defense.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
15.1. To develop a paralegal manual in coordination with the IPAJ; to develop ToRs; to select and contract technical experts; to select a printing agency.
-Distribute
[Added: 2010/02/22] |
UIP | 2012/12 | Overdue-Not Initiated | Activity for 2010 AWP. |
Management Response: [Added: 2010/02/22]
Annual planning meetings should be conducted with provincial offices; communication mechanisms should be established.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
16.1 To host planning meeting inviting provincial implementers.
[Added: 2010/02/22] |
UIP | 2010/03 | Overdue-Initiated | ||
16.2. To regularly share minutes of internal meetings, coordination meetings, technical meetings and PSC meetings with provincial offices.
[Added: 2010/02/22] |
UIP | 2010/12 | Overdue-Initiated |
Management Response: [Added: 2010/02/22]
Reporting templates and financial training were provided to the NGOs mid way during PACAJ implementation, and reporting improved substantially. However, with high turnover ratio, training needs are to be repeated, and close monitoring of report quality is necessary.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
17.1. Document to be prepared for helping implementing partners in reporting and result based management during phase 2.
[Added: 2010/02/22] |
UIP/Governance Unit | 2010/12 | Overdue-Not Initiated | ||
17.2. Document to be prepared to guide implementing partners in financial accountability and reporting during phase 2.
[Added: 2010/02/22] |
UIP/Governance Unit | 2009/12 | Overdue-Not Initiated |
Management Response: [Added: 2010/02/22]
The communication between the PACAJ, stakeholders, and members of the public will be improved by means of a quarterly newsletter to be distributed to justice institutions, donors, and the public by journalists.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
18.2. To develop and update PACAJ website.
[Added: 2010/02/22] |
UIP | 2010/12 | Overdue-Initiated | Website has been finalized; will be updated on a regular basis; 4 people have been trained | |
18.3. To disseminate.a pamphlet and a video on project results.
- To finalize a video of 30 minutes and a shorter version of 7 minutes.
- To develop a dissemination strategy for the video and a song on human rights
[Added: 2010/02/22] |
UIP | 2010/12 | Overdue-Initiated | Pamphlet has been produced; video is being produced; dissemination strategy is being drafted. | |
18.1. To develop a quarterly newsletter on PACAJ activities to disseminate project results.
[Added: 2010/02/22] |
UIP | 2009/12 | Completed | To continue in 2010 |
Management Response: [Added: 2010/02/22]
The strategy should be informed by the Study on women in the Justice Sector and Police, funded by the PACAJ.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
19.1 Design a team to analyze recommendations and develop further sector-wide gender strategy for the Justice sector.
[Added: 2010/02/22] |
UIP/Governance Unit | 2010/12 | Overdue-Not Initiated |
Management Response: [Added: 2010/02/22]
Poor financial and accountability capacity lead to stronger centralization of management during PACAJ. An attractive package and a training could contribute to improve capacity of accountants in provincial offices, and more flexible accountability measures could be established.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
20.1. To plan for high quality financial management in project offices for greater accountability and workflow.
[Added: 2010/02/22] [Last Updated: 2013/09/27] |
UIP/Governance Unit | 2010/12 | Completed | Design a team to take this into consideration. |
Management Response: [Added: 2010/02/22]
The project document should serve as a basis of the implementation strategy.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
21.1. The next phase shall develop an implementation strategy spelling out the roles of various stakeholders in the project and a monitoring and evaluation framework.
[Added: 2010/02/22] |
UIP/Governance Unit | 2011/12 | Overdue-Not Initiated |