Strengthening Community Safety through Local Government Capacity Building
Commissioning Unit: Jamaica
Evaluation Plan: 2007-2011
Evaluation Type: Project
Completion Date: 02/2011
Unit Responsible for providing Management Response: Jamaica
Documents Related to overall Management Response:
 
1. Recommendation: Share Findings of Project Baseline Survey, Mapping Exercise and Workplan with Key Stakeholders
Management Response: [Added: 2011/12/28]

Supported and built into the sustainability strategy of the project

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Consultation Event to share key project findings
[Added: 2011/12/28]
Governance Unit/ Project Team 2011/03 Completed Consultation Event Held in March 2011
Dissemination of information through Customised Course
[Added: 2011/12/28]
Governance Unit/ Department of Local Government, Faculty of the Built Environment, UTech No due date No deadline established Course Launched in September 2011
2. Recommendation: Only a few of the parish councilors were able to attend the training sessions in community safety audits. Reccommendation: Train Parish Councillors in Principles of Safety Audit
Management Response: [Added: 2011/12/28] [Last Updated: 2011/12/28]

supported and built into the sustainability strategy of the project

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Establishment of customized course
[Added: 2011/12/28]
Governance Unit/ Department of Local Government, Faculty of the Built Environment, UTech 2011/12 Overdue-Initiated Course launched in September 2011
Enroll parish councilors and key local government officials in WB Course on Urban Safety
[Added: 2011/12/28]
Governance Unit/ Department of Local Government 2011/12 Overdue-Initiated 16 participants enrolled in course
3. Recommendation: Community Safety Committees need technical support and training, especially in advocacy strategies to encourage greater responsiveness from state and local government entities to their submissions Reccommendation:Sustain Community Safety Committees
Management Response: [Added: 2011/12/28]

supported and built into the project?s Sustainability strategy

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Integration of the CSCs into the Crime Prevention and Community Safety Strategy
[Added: 2011/12/28]
Governance Unit 2011/12 Completed CSCs addressed under CPCSS
Support to the Community Renewal Programme and CPCSS local governance aspects
[Added: 2011/12/28]
Governance Unit 2011/12 Completed Integrated into follow-on Parish Safety Project
4. Recommendation: The same Project Board was asked to serve this project and the JVPPSD. However, a distinct and separate time of meeting is required for each project. This will avoid the perception of meetings being too long and insufficient time being spent on any of the projects. Reccommendation:Separate Project Boards for Each Project
Management Response: [Added: 2011/12/28]

Supported. Separate project Board Established

Key Actions:

Key Action Responsible DueDate Status Comments Documents
During LPAC Process Project Board Established
[Added: 2011/12/28]
Programme Team No due date No deadline established
Hold separate Final Project Board Meetings
[Added: 2011/12/28]
Programme Team/Project Team 2011/06 Completed Final Project Board meeting held on May 12 and for JVPPSDP on June 6, 2011
5. Recommendation: The project was piloted in 2 parishes, Clarendon and St. Catherine. However similar interventions were suggested for the other 11 parishes and municipalities Recommendation:Replication of Safety Audit Project
Management Response: [Added: 2011/12/28]

Supported, however the entire project?s replication is conditional on availability of resources for scale-up

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Integrate the lessons learned into follow-up Parish Safety Project
[Added: 2011/12/28]
Governance Unit 2011/04 Completed 2011 Parish Safety Project designed as a follow-on

Latest Evaluations