Management Response: [Added: 2014/05/12]
All the project tasks were completed
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
All tasks are completed
[Added: 2014/05/12] |
2014/05 | Completed |
Management Response: [Added: 2014/05/12]
Agree. Special training course was developed by UNDP for new key project staff, including Project Manager and Financial and Administrative Assistance and introduced into the routine CO practice.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Develop a special training course was developed by UNDP for new key project staff, including Project Manager and Financial and Administrative Assistance and introduced into the routine CO practice
[Added: 2014/05/12] |
UNDP CO | 2014/05 | Completed |
Management Response: [Added: 2014/05/12]
The issue should be brought to the CO Management. Respective issues should be identified, discussed and steps taken to improve cooperation between the CO and projects.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Inform the CO management of the problems
[Added: 2014/05/12] |
UNDP CO | 2014/05 | Completed | ||
Arrange a working meeting with CO and project staff to discuss the problems and define measures to improve the situation.
[Added: 2014/05/12] |
UNDP CO | 2014/05 | Completed |
Management Response: [Added: 2014/05/12]
Replication and sustainability of projects? successful experience and results is always the issue. The CO and the PMU made every effort to create enabling environment for integration of biodiversity concerns into national land use planning, including the development of the respective legal and regulatory basis and nation-wide information campaign. At the project design stage it was ensured that the project responded to the respective country priorities. However, additional follow-up measure should be taken to ensure replication of project successful experience and sustainability of the project results.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Arrange a meeting with the key national stakeholders to discuss and identify measures to ensure replication and sustainability.
[Added: 2014/05/12] [Last Updated: 2016/05/20] |
UNDP CO | 2014/12 | Completed | History | |
Exercise efforts to distribute the project results outside Belarus.
[Added: 2014/05/12] [Last Updated: 2016/05/20] |
UNDP CO | 2014/12 | Completed | History |
Management Response: [Added: 2014/05/12]
Agree. While wetlands are of importance for global and national biodiversity, other ecosystems should be given their faire share in terms of conservation efforts and respective TA from international organizations. However, a limited capacity and a small pool of expertise in the biodiversity field impede development of projects targeting other ecosystems. Consultations should be held with the ministry of environment, Belarusian scientific institutions and key experts to discuss this issue. Project ideas should be prioritized favoring other ecosystems when it is feasible and reasonable from the environmental point of view.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Discuss this issue with national counterparts.
[Added: 2014/05/12] |
UNDP | 2014/05 | Completed | ||
Prioritize project ideas favoring other ecosystems when it is feasible and reasonable from the environmental point of view
[Added: 2014/05/12] [Last Updated: 2016/05/20] |
UNDP | No due date | Completed | Throughout UNDP CO operation History |
Management Response: [Added: 2014/05/12]
Fully agree, Such flexibility would allow better response to changing situations and would lead to better use of limited allocated resources.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Bring this issue to and discuss with the BRC.
[Added: 2014/05/12] [Last Updated: 2016/05/20] |
UNDP CO | 2014/12 | Completed | History |
Management Response: [Added: 2014/05/12]
Agree. A discussion should be held with national counterparts, including environmental authorities, NGOs and SGP to discuss the situation and identify possible solutions. However, it should be noted that strengthening the Belarusian civil societies and professional maturing national environmental NOG is a lengthy process and cannot happen within a couple of years. Nevertheless, UNDP should acknowledge the problem and work towards improving NGOs capacity.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Arrange a meeting with the key stakeholders, including environmental authorities, NGOs and SGP to discuss the situation and identify possible solutions.
[Added: 2014/05/12] [Last Updated: 2016/05/20] |
UNDP CO | 2014/12 | Completed | History | |
Within projects plan actions to strengthen the capacity of Belarusian civil society organizations.
[Added: 2014/05/12] [Last Updated: 2016/05/20] |
UNDP CO | No due date | Completed | Throughout UNDP CO operation History |