Success message
error message
warn message
MTR: Strengthening Ecosystem Resilience and Community Adaptive Capacity in Climate Affected River Basins in DPRK (SERCARB)
Commissioning Unit: DPR Korea
Evaluation Plan: 2011-2019
Evaluation Type: Project
Completion Date: 12/2016
Unit Responsible for providing Management Response: DPR Korea
Documents Related to overall Management Response:
 
1. Recommendation:

Additional time for project activities needed

Management Response: [Added: 2016/12/29] [Last Updated: 2016/12/29]

Accepted

Key Actions:

Key Action Responsible DueDate Status Comments Documents
1.1. Re-phase/approve all remaining activities in next year AWP
[Added: 2016/12/29] [Last Updated: 2017/04/13]
SERCARB team, CO 2017/03 Completed History
1.2. Complete the activities in time, quantity and quality
[Added: 2016/12/29] [Last Updated: 2017/12/06]
SERCARB team 2017/12 Completed History
2. Recommendation:

Replicate the methods and approaches developed in an extension of the project in other communities

Management Response: [Added: 2016/12/29] [Last Updated: 2016/12/29]

Accepted

Key Actions:

Key Action Responsible DueDate Status Comments Documents
2.1. Develop and approve extension document
[Added: 2016/12/29] [Last Updated: 2017/12/06]
SERCARB team, CO, RBAP 2017/12 Completed CPD extension awaits for approval which is also the pre-condition for project's cost-extension. No CPD approved received as of December 2017 History
2.2. Plan activities in multi-years as per approved extension document
[Added: 2016/12/29] [Last Updated: 2017/12/06]
SERCARB team 2017/12 Completed CPD extension awaits for approval which is also the pre-condition for project's cost-extension History
2. 3. Complete the extension activities planned for replication in time, quantity and quality
[Added: 2016/12/29] [Last Updated: 2017/12/06]
SERCARB team 2017/12 Completed Since there is no CPD extension and thus the extension of the project, there will be no further activities under planned extension period History
3. Recommendation:

Maintain developed Methodology and implementation scheme

Management Response: [Added: 2016/12/29]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
3.1 The methodologies and implementation scheme will be maintained in the extension document
[Added: 2016/12/29] [Last Updated: 2017/04/13]
SERCARB team, CO, and BRH 2017/04 Completed On-going process, continue with improvements History
3.2 The methodologies and scheme will be continued and further improved in the course of extension / replication phase
[Added: 2016/12/29] [Last Updated: 2017/04/13]
SERCARB team 2017/04 Completed On-going process, continued with improvements History
4. Recommendation:

Review Output targets and indicators

Management Response: [Added: 2016/12/29]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
4.1 The targets and indicators found not SMART during the project review will be revised in the extension document
[Added: 2016/12/29] [Last Updated: 2017/04/13]
SERCARB team, CO, BRH 2017/03 Completed Final draft extension document ready with SMART indicators History
5. Recommendation:

Ensure coordination between project induced and stakeholder induced activities

Management Response: [Added: 2016/12/29]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
5.1 Improved coordination mechanism will be put in place at different levels in both existing pilot sites and sites to be replicated, for better synergies and results
[Added: 2016/12/29] [Last Updated: 2017/04/13]
SERCARB team 2017/04 Completed Duly noted and will be reflected in extension phase History
6. Recommendation:

Consolidate and strengthen MoLEP and SHMA capacities further

Management Response: [Added: 2016/12/29]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
6.1 Further in-country training and overseas exposure activities will be undertaken for local level staff of MOLEP and SHMA, to continue their capacity strengthening and ownership increase
[Added: 2016/12/29] [Last Updated: 2017/04/13]
SERCARB team 2017/04 Completed History
7. Recommendation:

Implement the community based parts of the EWS, while waiting for purchase of equipment

Management Response: [Added: 2016/12/29]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
7.1. Community based EWS will be finalized and training provided in the pilot communities, before and after the purchase of the equipment, with the CO’s cash conservation mode lifted.
[Added: 2016/12/29] [Last Updated: 2017/12/06]
SERCARB team 2017/12 Completed On track with implementation as of April 2017. EWS will be implemented as planned History

Latest Evaluations

Contact us

1 UN Plaza
DC1-20th Floor
New York, NY 10017
Tel. +1 646 781 4200
Fax. +1 646 781 4213
erc.support@undp.org