Commissioning Unit: | Armenia |
---|---|
Evaluation Plan: | 2010-2015 |
Evaluation Type: | Project |
Completion Date: | 07/2012 |
Unit Responsible for providing Management Response: | Armenia
|
Documents Related to overall Management Response: |
|
Key Action Update History
Management Response: [Added: 2014/05/09]
Accepted
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
To mainstream Social Cohesion in UNDP programming
[Added: 2014/05/09] [Last Updated: 2014/05/14] |
CO, DG Portfolio | 2014/12 | Completed |
Management Response: [Added: 2014/05/09]
Accepted
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Executive summary is prepared and included in the final report
[Added: 2014/05/09] |
DG Portfolio, Project | 2013/12 | Completed |
Management Response: [Added: 2014/05/09] [Last Updated: 2014/05/09]
Accepted
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
This is in process including through social media tools (Facebook)
[Added: 2014/05/09] |
DG Portfolio, Project | No due date | No deadline established |
Management Response: [Added: 2014/05/09]
Accepted with reservation; in absence of a dedicated media project this recommendation can be implemented in the frame of the CO communication strategy
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
To develop a work plan on promoting the SC concept through the media
[Added: 2014/05/09] [Last Updated: 2016/11/29] |
Project | 2016/12 | Completed | Addressed within the framework of the Women in Local Democracy Project implemented from 2012. The project included a standalone component of work with the media promoting women's participation in decision-making at local level. History |
Management Response: [Added: 2014/05/09]
Accepted with reservations: to that end UNDP should work at the level of strategic policy documents, ,e.g., National Sustainable Development Programme or post 2015 agenda
Key Actions:
Management Response: [Added: 2014/05/09]
Accepted
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
The SC approaches and prism are mainstreamed into UNDP DG Portfolio projects starting from end of 2011.
[Added: 2014/05/09] |
DG Portfolio | No due date | No deadline established |
Management Response: [Added: 2014/05/09]
Accepted
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
The follow up researches and discussions are planned in the framework of the Youth Studies Center to be established through the Support to the Establishment of the Youth Studies Center Project implemented by UNDP with DGTTF funding.
[Added: 2014/05/09] [Last Updated: 2014/05/14] |
DG Portfolio | 2014/05 | No Longer Applicable | Through consultations with the national counterparts, the prioritization of research topics for Youth Research Center changed to: i) Youth Independent Index, ii)Youth employment, and iii) Mapping of Youth Organizations. |
Management Response: [Added: 2014/05/09]
Accepted with reservation in view of the overall sensitivity of electoral processes; UNDP?s view is that promotion of the concept of SC can be most efficient in-between the elections.
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
Revisit this recommendation after the presidential elections scheduled for February 2013
[Added: 2014/05/09] [Last Updated: 2014/05/14] |
No due date | No deadline established | 1) Not applicable for Political Parties. 2) Idea was discussed at the Local Self-Governance level e.g., at the LSG Annual National forums and gatherings of 2012 and 2013. UNDP is promoting the concept of social cohesion at the high level forums related to local governance reforms. |
Management Response: [Added: 2014/05/09]
Accepted
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
1 The results were already used in Live Armenia, Women in Local Democracy and Support to Establishment of the Youth Studies Center projects. Also, the Community Development Project of the Socio-Economic Governance Portfolio as well as the Live Armenia Project of DG Portfolio are both connected with community issues, community budget development and joint implementation of community projects.
[Added: 2014/05/09] [Last Updated: 2014/05/14] |
DG and EG Portfolios | 2014/05 | No Longer Applicable | Due to limited Country Office resources |
Management Response: [Added: 2014/05/09]
Accepted
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
The CO will discuss with the Regional Service Center a possibility to develop for the Ministry of Territorial Administration a user-friendly indicator on Social Cohesion disaggregated by regions
[Added: 2014/05/09] |
DG Portfolio, MTA, RSC | No due date | No deadline established |
Management Response: [Added: 2014/05/09]
Accepted
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
At this stage the CO has tentatively planned to conduct another survey in 2014 to reflect the findings in post 2015 national development agenda
[Added: 2014/05/09] |
DG Portfolio, Country Office | No due date | No deadline established |
Management Response: [Added: 2014/05/09]
Not accepted, since to prepare the ToR of this first -ever research on SC in Armenia the DG Portfolio conducted a comprehensive research/ desk review of similar initiatives and also held a round of extensive consultations with the counterparts from UN agencies, government and civil society
Key Actions:
Management Response: [Added: 2014/05/09]
Accepted
Key Actions:
Key Action | Responsible | DueDate | Status | Comments | Documents |
---|---|---|---|---|---|
The Advisory Board approach will be applied in other projects as deemed necessary
[Added: 2014/05/09] |
DG Portfolio | No due date | No deadline established |
Management Response: [Added: 2014/05/09]
Agreed with the proposed approach which is at heart of UNDP mandate and UNDP continuously promotes active collaboration and dialogue between the CSO and the State in all projects