Commissioning Unit: | Mauritius |
---|---|
Evaluation Plan: | 2009-2011 |
Evaluation Type: | Project |
Completion Date: | 12/2012 |
Unit Responsible for providing Management Response: | Mauritius
|
Documents Related to overall Management Response: |
|
Key Action Update History
Management Response: [Added: 2013/01/31]
Partnership between international and local companies was organized for the consultancy on Disaster Risk Reduction. For other activities, the consultant teams always came to Mauritius and strongly linked with relevant stakeholders during preparation of work, presentation of findings and incorporation of feedbacks.
Key Actions:
Management Response: [Added: 2013/01/31]
Time and budget constraints did not allow this kind of evaluation exercise during the AAP. Moreover, evaluation of training impacts might be a challenge due to regular staff transfers within public bodies. Advocacy will be conducted by UNDP CO on the importance of evaluation of activities? impacts, for next projects.
Key Actions:
Management Response: [Added: 2013/01/31]
Agreed. Attendance sheets will be compiled by the Project Team after project closure to create the database.
Key Actions:
Management Response: [Added: 2013/01/31]
Time and budget constraints did not allow this kind of evaluation exercise during the AAP. Advocacy will be conducted by UNDP CO on the importance of evaluation of activities? impacts, for next projects.
Key Actions:
Management Response: [Added: 2013/01/31]
Although the activity has been delayed due to procurement issues with UNOPS, this recommendation will be addressed by the final setting up of the Climate Change Information Center, in January 2013.
Key Actions:
Management Response: [Added: 2013/01/31]
This issue will have to be discussed by the Government of Mauritius, based on the needs of various ministries, especially in relation to Climate Change.
Key Actions:
Management Response: [Added: 2013/01/31]
This issue will have to be discussed by the Government of Mauritius, especially with Ministry of Environment and Sustainable Development and Ministry of Education.
Key Actions:
Management Response: [Added: 2013/01/31]
Awareness week, Climate Change Knowledge Fair, mobile exhibition all address the need for dissemination of knowledge. In addition, although delays were experienced, Information, Education and Communication campaign has been organized in December-January 2013.
Key Actions:
Management Response: [Added: 2013/01/31]
T21 was not considered a priority by the Government during AAP. This model has proven itself very useful in other AAP countries such as Kenya and development of such a model (T21 or equivalent) for Mauritius will be advocated by UNDP CO.
Key Actions:
Management Response: [Added: 2013/01/31]
This recommendation will have to be studied by Ministry of Fisheries and Marine Resources, together with the private sector.
Key Actions:
Management Response: [Added: 2013/01/31]
This issue will have to be discussed by the Government of Mauritius, especially with the Met Services and other ministries dealing with Climate Change adaptation. Already identified, this issue is also partly answered by the new UNDP-supported Climate Change adaptation project for the coastal zones of Mauritius (AFB), which includes an ?early-warning? component. Dialogue with the Met Services is already open to assess training and equipment needs.
Key Actions:
Management Response: [Added: 2013/01/31]
Agreed. UNDP CO will monitor the sustainability of AAP achievements and work with the Government, and especially Ministry of Environment and Sustainable Development to identify further needs in the area of Climate Change adaptation. This has already been partly done through the mobilization of a 9,000,000 USD grant from the Adaptation Fund Board, allowing a follow up on many AAP activities.
Key Actions:
Management Response: [Added: 2013/01/31]
This issue will have to be addressed by the Government of Mauritius. Advocacy will be conducted by UNDP CO to support the organization of this discussion and of this study, securing funds if possible.
Key Actions:
Management Response: [Added: 2013/01/31]
Agreed. In the case of the AAP, the design was made at regional level, with little possibility of tailoring to national contexts. This will be took into account for next projects as far as possible.
Key Actions:
Management Response: [Added: 2013/01/31]
Agreed. Stakeholders? involvement during project development and drafting also allows increased relevancy and ownership of logframes.
Key Actions:
Management Response: [Added: 2013/01/31]
Partially agreed. The strategic dimension of the PSC is very important but it is crucial that committed persons attend the PSC, which is not always the case for high-level policy-makers. The AAP PSC worked efficiently during the project. Policy dialogue was also made at Cabinet when main AAP results were transmitted.
Key Actions:
Management Response: [Added: 2013/01/31]
Agreed. Such meetings were held internally at the Ministry of Environment at the end of the project and proved themselves to be very efficient. The process should be made systematic with main stakeholders for next projects.
Key Actions:
Management Response: [Added: 2013/01/31]
Partially agreed. A representative of Rodrigues attended the PSC as often as possible, but the logistic sometimes prevented him to do so. The question of representativity in Rodrigues is also very political.
Key Actions:
Management Response: [Added: 2013/01/31]
Agreed. The M&E activities were often disregarded in favor of implementation due to delays, but this should not be the case for future projects as M&E allows being more efficient in the long term.
Key Actions:
Management Response: [Added: 2013/01/31]
Agreed. Refer to 1.2, 1.4 and 2.6.
Key Actions:
Management Response: [Added: 2013/01/31]
Agreed. This has already started for new project.
Key Actions:
Management Response: [Added: 2013/01/31]
Agreed.
Key Actions: