Project Final Evaluation of UNDP/GEF Strengthening Capacity for an Environmental Information Management and Monitoring System in Tajikistan
Commissioning Unit: Tajikistan
Evaluation Plan: 2016-2020
Evaluation Type: Project
Completion Date: 11/2017
Unit Responsible for providing Management Response: Tajikistan
Documents Related to overall Management Response:
 
1. Recommendation:

1. Recommendation: CCCD Project has to ensure that all deliverables are delivered by Softline IT, responsible for Design and Development of a Database and Environmental Monitoring System.

Management Response: [Added: 2018/03/15]

acknowledged 

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Oversight of the design and development of a database and an environmental monitoring system will be ensured
[Added: 2018/03/15]
Project Manager/EEP Manager 2018/01 Completed
2. Recommendation:

2. Recommendation: Operationalization of EIMMS software to be completed.

Management Response: [Added: 2018/03/15]

To ensure “transfer of knowledge” to the newly established the National and Local Environmental Monitoring Centers.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
1) Build capacity of CEP and transfer the operational knowledge to staff and other government officials; 2) Support the competent agency in running the new system, improving operations and systems’ management including performance monitoring, back-up retention/recovery, and business continuity; 3) Draft user and technical manuals for e-Reporting module and database use for users and administrators.
[Added: 2018/03/15]
Softline IT 2018/01 Completed