00083160 Reducing Releases of Polybromodiphenyl Ethers (PBDE) in Indonesia GEF Mid-Term Evaluation
Commissioning Unit: Indonesia
Evaluation Plan: 2016-2020
Evaluation Type: Project
Completion Date: 09/2019
Unit Responsible for providing Management Response: Indonesia
Documents Related to overall Management Response:
 
1. Recommendation:

The number of mini depot to be developed is three, located in Cirebon, Malang, and Depok. The three mini depots should reduce hazardous and unrecyclable plastic. 

Management Response: [Added: 2019/08/06]

The project has conducted meetings with Ministry of Industry to establish three mini depots in the beginning of the project and the target each mini depot should achieve.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
1. Develop contact with prospective agencies and/or local governments in which mini depots will be consructed. 2. Discuss the technical matters with the project prospective partners (agencies, or local governments) and consultants in regards with the development of mini depots in three locations. The tehcnical matters include the building construction, machine specifications, feasibility studies, environment studies, economic studies, and environment studies.
[Added: 2019/08/20] [Last Updated: 2020/02/11]
UNDP CO and Implementing partner 2021/01 Initiated History
2. Recommendation:

PBDE Project recommends that -- while mini depots are still in progress and not able to work on plastic disposal – an effort to safely dispose PBDE containing plastic should be done with third parties (recyclers, cement kiln, hazardous waste companies).  

Management Response: [Added: 2019/08/06]

PBDE project has developed communications with some parties who have capabilites in disposing hazardous wastes.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Develop contact with cement industries and companies who have expertise in hazardous waste disposal.
[Added: 2019/08/20] [Last Updated: 2020/02/11]
UNDP CO Indonesia and Implementing partner 2021/01 Initiated History
3. Recommendation:

PBDE Project recommends “no additional cost” extension of nine months, in order to allow the project to complete component 3 and 4  

Management Response: [Added: 2019/08/20]

The project conducted a series of meeting with Ministry of Industry as the implementing partner to repsond the recommendations from MTR finding and to discuss the extension of the project.

This recommend will be discussed in the project board meeting on 31 Juli 2019

Key Actions:

Key Action Responsible DueDate Status Comments Documents
Conduct meetings with Ministry of Industri as the implementing partner regarding the posibility of extension. The discussion also focus on the timeline schedule and budget to spend for the extension.
[Added: 2019/08/20] [Last Updated: 2020/01/16]
UNDP CO and Implementing partner 2019/12 Completed The meeting had been conducted engaging the Ministry of Industry as implementing partner History