Terminal Evaluation: Recovery and Resilience in Selected Typhoon Yolanda-affected Communities in the Visayas
Commissioning Unit: Philippines
Evaluation Plan: 2012-2018
Evaluation Type: Project
Completion Date: 05/2018
Unit Responsible for providing Management Response: Philippines
Documents Related to overall Management Response:
 
1. Recommendation:

1. On Resilient Infrastructure: Designers of future CECs and related infrastructure should integrate knowledge of local conditions such as prevailing wind conditions during rainy season. As such, local engineers or engineering firms should be involved in the design of infrastructure that will be responsive to the needs of local communities in times of disastrous events.

Management Response: [Added: 2018/11/29]

This recommendation and accepted and will be taken into consideration for future projects that will have Community Evacuation Centers as one of its outputs.

Key Actions:

Key Action Responsible DueDate Status Comments Documents
This recommendation will be applied to future projects that will have Community Evacuation Centers as one of its outputs. The evaluation and its recommendations will be shared with the Inclusive and Sustainable Development Unit for application in Project RAPID.
[Added: 2018/11/29]
CO, Resilience and Peace Building Unit 2018/12 Completed