Success message
error message
warn message
SOI Integrating global environment commitments in investment and development decision-making in Solomon Islands
Commissioning Unit: Fiji
Evaluation Plan: 2018-2022
Evaluation Type: Project
Completion Date: 10/2018
Unit Responsible for providing Management Response: Fiji
Documents Related to overall Management Response:
 
1. Recommendation:

Produce more hard copies of the guidelines, EIA checklists, the framework, and other project’s deliverables and make them available for national stakeholders.

Management Response: [Added: 2018/10/11] [Last Updated: 2018/10/31]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
1.1. Printing of the EIA checklists and project deliverables to distribute within key ministries and communities
[Added: 2018/10/30] [Last Updated: 2018/11/14]
UNDP/MOFR 2018/11 Completed Printing has been completed and distribution has been done within key ministries and communities History
1.2 Collaborate with MoFR RIU to up load all documents on the website
[Added: 2018/10/30]
UNDP/MOFR 2019/03 Initiated Discussion with MOFR REDD+ unit underway
2. Recommendation:

The valuable public awareness products, mainly the secondary schools textbook and teachers’ guide, produced by the project on the Rio Conventions should be distributed to all stakeholders mainly to the Ministry of Education and a large number of high schools.

Management Response: [Added: 2018/10/11] [Last Updated: 2018/10/31]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
2.1. Distribution of secondary school text book and teachers guide to Solomon Islands National University and Secondary schools in Solomon Islands
[Added: 2018/10/30]
UNDP and Ministry of Education 2019/06 Initiated Once the printing is done the distribution of books will be carried out by Ministry of Education
2.2. Collaborate with FAO IFM project and TNC through MOFR to build on the project’s awareness and pilot program
[Added: 2018/10/30]
UNDP and MOFR 2019/06 Initiated Discussion prior to the project closure has already been underway and is captured in the minute of the final board meeting
3. Recommendation:

While this TE was not able to analyze the training-manuals developed and implemented by the projects, it is recommended that the remaining project training and piloting activities be completed as soon as possible, including texting the training manuals that incorporating standardized local friendly methods for community-based ecosystem assessments for REDD+ projects, the proposed amendments to the Environment Act and Environment Regulations, and piloting the testing of an innovative forest management approach framed by REDD+ that aimed to demonstrating measurable indicators of delivering global environment benefits. (UNDP, and MECDM).

Management Response: [Added: 2018/10/11] [Last Updated: 2018/10/31]

Agreed in Principle

Key Actions:

Key Action Responsible DueDate Status Comments Documents
3.1. Complete the pilot activity with support from FAO IFM project
[Added: 2018/10/30]
UNDP, MECDM,MOFR 2019/06 Initiated Discussion is already underway with MOFR and FAO IFM project to implement the pilot project
4. Recommendation:

Mainstreaming Rio Convention in decision-making process capacity presently has limitations to meet the actual needs at the Country level.

Management Response: [Added: 2018/10/11] [Last Updated: 2018/10/31]

Agreed

Key Actions:

Key Action Responsible DueDate Status Comments Documents
4.1 Under the REDD+ task force and the donor forestry task force will continue to build on the work on the project through the assessment report to mainstream into new and current programmes by development partners and donors
[Added: 2018/10/30] [Last Updated: 2018/11/14]
MECDM, MOFR, FAO,GIZ,UNDP, 2019/06 No Longer Applicable [Justification: As mentioned in the comments below there is no time-frame for this recommendation as it is ongoing. Thus, it is no longer applicable. ]
There would be no end time-frame for this recommendation as it is ongoing and that is something key partners want to see happening as an outcome of the project. History

Latest Evaluations

Contact us

220 East 42nd Street
20th Floor
New York, NY 10017
Tel. +1 646 781 4200
Fax. +1 646 781 4213
erc.support@undp.org