Evaluation Plan of 2017-2021
Plan Detail (2017-2021)
Commissioning Unit:
Belize
Period :
2017-2021
Status:
Posted
Comments :
The 2017-2021 Evaluation Plan was prepared as part of the new 2017-2021 Country Programme Document and approved by the UNDP Executive Board in September 2016. Monitoring and Evaluation will be carried out in line with the MSDF results matrix. The Evaluation Plan covers all mandatory evaluations, all required project evaluations and any other evaluation of strategic importance. Where applicable and feasible, the lessons learnt from evaluations will be incorporated into ongoing or new projects and programmatic actions. it is noteworthy to mention that the evaluation plan is not a static document and may require adjustment as circumstances change. Adjustments to individual evaluations and the evaluation plan will be considered annually as part of the programme unit’s stocktaking exercise. Programme units should discuss possible changes with regional focal points prior to making and requesting adjustments to plans through the Evaluation Resource Centre. Changes, particularly deletions, to individual project evaluations should be discussed, agreed and noted in minutes with project management boards or their equivalents such as a steering committee.
Plan Document:
BLZ_EVALUATION PLAN UPDATED FEBRUARY 22 2019.pdf

Evaluations Commissioned by Belize

SN Title Type Partners (Joint Evaluations) Planned End Date Completion Date Key Stake holders Resource
& Fund Source
Status Reports Mgmt.
Resp
1. Referendum on Border Dispute End of Project Evaluation Project Dec 2019 Ministry of Foreign Affairs, Elections & Boundaries Department, Belize Network of NGOs $10,000 Planned
2. Final Country Programme Document Evaluation Country Programme Evaluation Dec 2021 Ministry of Economic Development, Ministry of Agriculture, Fisheries, Forestry, the Environment, Sustainable Development and Climate Change $30,000 Planned
3. Evaluation of Governance/ Citizen Security Portfolio Outcome Aug 2019 Ministry of Human Development, Restore Belize Department of Youth services ,Ministry of National Security, KOBE Foundation, UNICEF $15,000 Planned
4. Evaluation of Energy/ Environment/ Climate Change/ Sustainable Development Portfolio Outcome Aug 2019 Ministry of Economic Development, Ministry of Agriculture, Fisheries, Forestry, the Environment, Sustainable Development and Climate Change $15,000 Planned
5. Terminal Evaluation of Belize Chemicals and Waste Management Project Project May 2019 Miniistry of Fisheries, Forestry and Sustainable Development, Department of Environment, Ministry of Agriculture, Ministry of Health, Pesticides Control Board $12,000 Overdue
6. Investing for Impact against TB & HIV in Belize Project Mar 2019 Ministry of Health BFLA Hand in Hand Ministries POWA $25,000 Cancelled
7. Terminal Evaluation of Capacity-building for the strategic planning and management of natural resources in Belize Project May 2019 Miniistry of Fisheries, Forestry and Sustainable Development, Ministry of Natural Resources and Agriculture, Ministry of Public Service, MInistry of Economic Development $14,000 Overdue
8. UNCAC End of Project Evaluation Project Dec 2019 Attorney General's Ministry, Belize Chamber of Commerce & Industry, Belize Network of NGOs, Opposition, Belize Council of Churches, Belize Youth Council $10,000 Planned
9. Mid-term Country Programme Document Evaluation Country Programme Evaluation Dec 2019 Ministry of Economic Development $15,000 Planned