Union Parishad Governance Project (UPGP) & Upazila Governance Project (UZGP) Midterm Evaluation
Completedon 21 Dec, 2014
Evaluation Plan
Planned End Date
Dec 2014
Evaluation Type
Project
Management Response
Yes
Evaluation Budget
$206,000
Evaluation Title
Union Parishad Governance Project (UPGP) & Upazila Governance Project (UZGP) Midterm Evaluation
Plan Period
Status
Completed
Type
Project
Plan Date
1 Dec, 2014
Completion Date
21 Dec, 2014
Budget
$206,000
Expenditure
$0
Source of Funding
Donor resources
Management Response
Yes
Quality Assessment
No
Joint Programme
No
Joint Evaluation
No
GEF Evaluation
No
Stakeholders
Ministry of Local Government, Donors, UN Agencies
Countries
Bangladesh
Comments
Yes
Expand
Plan Period
Status
Completed
Type
Project
Management Response
Yes
Plan Date
1 Dec, 2014
Quality Assessment
No
Completion Date
21 Dec, 2014
Joint Programme
No
Joint Evaluation
No
Budget
$206,000
GEF Evaluation
No
Expenditure
$0
Stakeholders
Ministry of Local Government, Donors, UN Agencies
Source of Funding
Donor resources
Countries
Bangladesh
Comments
Yes
Expand
Output 3.2. Functions, financing and capacity of sub-national level institutions enabled to deliver improved basic services and respond to priorities voiced by the public
1: Others